The bid work “XXI.1.11. hay barn and fodder reservoirs warehouse /inter provinces encampment area /” arranged by the procurement authority Lot 1: had been completed successfully and had been commissioned into exploitation. 236,6 million tugrugs had been spent from the state budget.
The Partnership of “Durvun-Zet" Company and “Baatar Shuteen Uul" Company were selected in a bid to implement this work. The companies constructed it for the period from June 10, 2014 until September 30, 2014 and handed over the bid work within the contract schedule.
The bid work “XXI.1.11. hay barn and fodder reservoirs warehouse /inter provinces encampment area /” in Malah encampment pasture area in Sumber soum of Gobisumber province Lot 2: had been completed successfully and had been commissioned into exploitation. 239 million tugrugs had been spent from the state budget. “Khuchit Chuluut“Company was selected in a bid to implement this work. It constructed it for the period from June 10, 2014 until September 30, 2014 and handed over the bid work within the contract schedule.